Removal (Plug and Abandon)Extraction Oil and Gas has notified the Town of Erie that they will begin a plug and abandon operation within Erie limits (east of the North Water Reclamation Facility, north of Hwy 52) on the 'Cinque Federal 7-31' well site.
According to Extraction, the operation is expected to begin on or around March 16, 2020 and will "take approximately 7-10 days to complete, however, it could take longer if there are issues at the site. Equipment necessary to complete this job include a workover rig, 3 winch trucks, a water truck, 2 semi-trucks for cement ops and 1 for wireline work, a combustor trailer, a separator trailer, and various pickup trucks. There will be up to 8 people on site, and all work will remain on the pad and lease road."
|