Coal Creek Park

The redevelopment includes a new event lawn, entrance plaza, 2,000 sf restroom and picnic shelter building, an additional shade structure, two playground areas, additional parking with EV charging stations, splash pad, and a multi-use area that will house the Town's ice rink, complete with enclosures to house ice rink equipment.

Coal Creek Park Grand Reopening Celebration!

Join us on Friday, June 16 from 4-7 p.m. at Coal Creek Park, located at 575 Kattell Street, as we reopen this park. Celebration will include a grand opening ceremony, splash pad opening, raffle, kids entertainment, live music provided by The Montage Band, Kona Ice, and more!

Schedule of Events

  • 4 p.m.: Grand Opening Ceremony
  • 4: 25 p.m. Splash Pad Opening
  • 4:30 p.m.: Raffle Prize Drawing
  • 4:30 p.m.: Kids Entertainment and Vendor Booths Available
  • 5-7 p.m.: Live Music

Times are approximate and subject to change. 

Project Progress

February 2023 Progress

  • Playground installation is well underway! 
  • The McDaniel family was able to honor their daughter, Maddie, and witness the installation of the butterfly play structure at Maddie's Playground.

January 2023 Progress

  • Xcel has finished tying in power to the site, the structure that will house the splash pad equipment and additional storage space is complete and playground install crews have been busy drilling holes and pouring concrete footers.

December 2022 Progress

  • Contractors are putting the finishing touches on electrical, fiber, and plumbing equipment at the buildings on site as conditions allow. The electrical and fiber will enable other contractors to begin installing equipment for security cameras and WiFi access points. 
  • Plumbing contractors are finalizing locations for the potable and irrigation water sources to prepare for spring landscaping installation.

November 2022 Progress

  • The Coal Creek Park Community Building is about 60% complete.
  • Silva cells are a relatively new way to plant trees in paver spaces. In a typical install, trees are planted within a small area, backfilled, and pavers placed around them. This can cause heaving as the tree matures. Silva cells create a large “void” of soil for roots of trees several feet under the pavers that encourage roots to grow “down” vs. “out.”
  • The splash pad concrete has been poured and the plumbing system is installed. The building that will house the control system will start to go vertical in the next month.
  • Site amenities (benches, tables, etc.) have been delivered and will start getting installed as conditions allow. The playground equipment is scheduled for install this month.

Project Videos